Spending MVR 59.35 million from the state budget on a project to install parking systems in Malé and Hulhumalé without delivering any benefit to the public amounts to negligence of state funds, according to an audit report on the Housing Ministry covering 2018 to 2023.
The report states that this was an unauthorised act in violation of the Public Finance Regulation, and the Auditor General's Office has advised that the matter be investigated and action taken against anyone found to have been negligent.
According to the report, the State Trading Organisation (STO) was contracted on 26 June 2016 to install parking systems in 20 areas of Malé and Hulhumalé for MVR 59.9 million. However, when the agreement was terminated on 26 June 2018 on the grounds that work was not progressing adequately, only two systems had been completed.
Later in 2018, a foreign company was contracted for MVR 14.4 million to install the 14 remaining incomplete systems. Although more than MVR 4 million was paid to the company against two invoices, the report notes that it cannot be determined which area's system the payments related to or how much of the work had been completed.
In addition, while the Public Finance Regulation requires bills for works exceeding MVR 2.5 million to be paid only after reviewing a consultant's report, the audit found that MVR 9.8 million was paid against four bills submitted by STO without verifying the extent of work completed.
The report also states that although conducting a feasibility study is important before starting major projects, there is no documentation showing that such a study was carried out before this project began. The ministry informed the Audit Office that although STO handed over to the ministry the materials brought in to install the systems after the work was halted, it does not know what became of those materials.